lexiara

Section 88(2)

PA 2023
Procurement Act 2023 · United Kingdom

Any sum due to be paid under the contract by the contracting authority must be paid before the end of the period of 30 days beginning with— the day on which an invoice is received by the contracting authority in respect of the sum, or if later, the day on which the sum first became due in accordance with the invoice.

· All articles ·

Source: legislation.gov.uk · retrieved 2026-09-04