Schedule 25C, paragraph 8(5)
The Environmental Permitting (England and Wales) Regulations 2016 · United Kingdom
Paragraph 8(1) does not apply in respect of— an existing medium combustion plant within the meaning of paragraph 2(1) of Schedule 25A with a rated thermal input of less than or equal to 5 megawatts, or a Tranche A generator within the meaning of paragraph 3(3) of Schedule 25B with a rated thermal input equal to or less than 5 megawatts.