Schedule 5, Part 1, paragraph 16(2)

The period starts— in the case of an application for the grant or variation of an environmental permit in relation to a Category A mining waste facility— on the day the regulator is notified by the fire and rescue authority of the matters referred to in paragraph 14(1) of Schedule 20, and for these purposes “fire and rescue authority” has the meaning given in paragraph 2 of that Schedule, or if paragraph 10 of this Schedule applies, on the day mentioned in sub-paragraph (i) of this paragraph or, if the day on which the appropriate authority complies with paragraph 10(3) of this Schedule is later, on that day; if paragraph 10 of this Schedule applies and the application is not one covered by paragraph (a), on the day the appropriate authority complies with paragraph 10(3) of this Schedule; in all other cases, on the day the regulator receives a duly-made application.