Amounts of compensation determined under this Part are payable— where the operator and either the grantor or mortgagee agree that a single payment is to be made on a specified date, on that date; where the operator and either the grantor or mortgagee agree that payment is to be made in instalments at different dates, on the date agreed as regards each instalment; in any other case, subject to any direction of the Upper Tribunal or the court, as soon as reasonably practicable after the amount of the compensation has been determined.