Section 89(4)
The Conservation of Habitats and Species Regulations 2017 · United Kingdom
Where the consent is to construct or extend, but also to operate, a generating station, the works, if not already completed when the generating station is first operated in reliance on the consent, are to be treated as completed at that date.