The review provisions apply to an authorisation mentioned in paragraph (1) unless— the works to which the authorisation relates— were completed before 30th October 1994; or have been completed before the site became a European site , a Ramsar site or a European offshore marine site (as the case may be); or the authorisation was granted— subject to a condition as to the time within which the works to which it relates were to be begun and that time has expired without those works having been begun; or for a limited period and that period has expired.