| 18 | Costs that may be attributable to contract activity in general and can be allocated to specific contracts include: (a) insurance; (b) costs of design and technical assistance that are not directly related to a specific contract; and (c) construction overheads. Such costs are allocated using methods that are systematic and rational and are applied consistently to all costs having similar characteristics. The allocation is based on the normal level of construction activity. Construction overheads include costs such as the preparation and processing of construction personnel payroll. Costs that may be attributable to contract activity in general and can be allocated to specific contracts also include borrowing costs when the contractor adopts the allowed alternative treatment in IAS 23 Borrowing costs.