| 23 | In the case of a fixed price contract, the outcome of a construction contract can be estimated reliably when all the following conditions are satisfied: (a) total contract revenue can be measured reliably; (b) it is probable that the economic benefits associated with the contract will flow to the entity; (c) both the contract costs to complete the contract and the stage of contract completion at the balance sheet date can be measured reliably; and (d) the contract costs attributable to the contract can be clearly identified and measured reliably so that actual contract costs incurred can be compared with prior estimates.