doc__table__334
| 24 | In the case of a cost plus contract, the outcome of a construction contract can be estimated reliably when all the following conditions are satisfied: (a) it is probable that the economic benefits associated with the contract will flow to the entity; and (b) the contract costs attributable to the contract, whether or not specifically reimbursable, can be clearly identified and measured reliably.
← doc__table__333 · All articles · doc__table__335 →
Source: EUR-Lex (Cellar) · retrieved 2026-11-08 · Text as adopted (Official Journal); later amendments are not incorporated in this text.