| 24 | In the case of a cost plus contract, the outcome of a construction contract can be estimated reliably when all the following conditions are satisfied: (a) it is probable that the economic benefits associated with the contract will flow to the entity; and (b) the contract costs attributable to the contract, whether or not specifically reimbursable, can be clearly identified and measured reliably.