Article 47 › 3
Contracting authorities shall extend the time limits for the receipt of tenders so that all economic operators concerned may be aware of all the information needed to produce tenders in the following cases: (a) where, for whatever reason, additional information, although requested by the economic operator in good time, is not supplied at the latest six days before the time limit fixed for the receipt of tenders. In the event of an accelerated procedure as referred to in Article 27(3) and Article 28(6), that period shall be four days; (b) where significant changes are made to the procurement documents.