(8) A common grid model for single day-ahead and intraday coupling purposes representing the European interconnected system should be established to calculate cross-zonal capacity in a coordinated way. The common grid model should include a model of the transmission system with the location of generation units and loads relevant to calculating cross-zonal capacity. The provision of accurate and timely information by each TSO is essential to the creation of the common grid model.