Article 101
The outage planning agent of a relevant asset the availability status of which has been declared as ‘testing’ shall provide the TSO, and, if connected to a distribution system, including closed distribution systems, the DSO or the CDSO within 1 month before the start of the ‘testing’ status, with: a detailed test plan; an indicative generation or consumption schedule if the concerned relevant asset is a relevant power generating module or a relevant demand facility; and changes to the topology of the transmission system or distribution system if the concerned relevant asset is a relevant grid element. The outage planning agent shall update the information referred to in paragraph 1 as soon as it is subject to any change. The TSO of a relevant asset the availability status of which has been declared as ‘testing’ shall provide the information received in accordance with paragraph 1 to all other TSOs of its outage coordination region(s), upon their request. Where the relevant asset referred to in paragraph 1 is a relevant grid element interconnecting two or more control areas, the TSOs of the concerned control areas shall agree on the information to be provided pursuant to paragraph 1.
← CHAPTER 3 · All articles · 1. →
Source: EUR-Lex (Cellar) · retrieved 2026-11-04 · Text as adopted (Official Journal); later amendments are not incorporated in this text.