1.
The outage planning agent of a relevant asset the availability status of which has been declared as ‘testing’ shall provide the TSO, and, if connected to a distribution system, including closed distribution systems, the DSO or the CDSO within 1 month before the start of the ‘testing’ status, with: a detailed test plan; an indicative generation or consumption schedule if the concerned relevant asset is a relevant power generating module or a relevant demand facility; and changes to the topology of the transmission system or distribution system if the concerned relevant asset is a relevant grid element.