Article 52
Unless otherwise provided by the TSO, each transmission-connected demand facility owner shall provide the following structural data to the TSO: electrical data of the transformers connected to the transmission system; characteristics of the load of the demand facility; and characteristics of the reactive power control. Unless otherwise provided by the TSO, each transmission-connected demand facility owner shall provide the following data to the TSO: scheduled active and forecasted reactive power consumption on a day-ahead and intraday basis, including any changes of those schedules or forecast; any forecasted restriction in the reactive power control capability; in case of participation in demand response, a schedule of its structural minimum and maximum power range to be curtailed; and by exception to point (a), in regions with a central dispatch system, the data requested by the TSO for the preparation of its active power output schedule. Unless otherwise provided by the TSO, each transmission-connected demand facility owner shall provide the following data to the TSO in real-time: active and reactive power at the connection point; and the minimum and maximum power range to be curtailed. Each transmission-connected demand facility owner shall describe to its TSO its behaviour at the voltage ranges referred to in Article 27.
← CHAPTER 6 · All articles · 1. →
Source: EUR-Lex (Cellar) · retrieved 2026-11-04 · Text as adopted (Official Journal); later amendments are not incorporated in this text.