CHAPTER 6
Unless otherwise provided by the TSO, each transmission-connected demand facility owner shall provide the following structural data to the TSO: electrical data of the transformers connected to the transmission system; characteristics of the load of the demand facility; and characteristics of the reactive power control. Unless otherwise provided by the TSO, each transmission-connected demand facility owner shall provide the following data to the TSO: scheduled active and forecasted reactive power consumption on a day-ahead and intraday basis, including any changes of those schedules or forecast; any forecasted restriction in the reactive power control capability; in case of participation in demand response, a schedule of its structural minimum and maximum power range to be curtailed; and by exception to point (a), in regions with a central dispatch system, the data requested by the TSO for the preparation of its active power output schedule. Unless otherwise provided by the TSO, each transmission-connected demand facility owner shall provide the following data to the TSO in real-time: active and reactive power at the connection point; and the minimum and maximum power range to be curtailed. Each transmission-connected demand facility owner shall describe to its TSO its behaviour at the voltage ranges referred to in Article 27. Unless otherwise provided by the TSO, each SGU which is a distribution-connected demand facility and which participates in demand response other than through a third party shall provide the following scheduled and real-time data to the TSO and to the DSO: structural minimum and maximum active power available for demand response and the maximum and minimum duration of any potential usage of this power for demand response; a forecast of unrestricted active power available for demand response and any planned demand response; real-time active and reactive power at the connection point; and a confirmation that the estimations of the actual values of demand response are applied. Unless otherwise provided by the TSO, each SGU which is a third party participating in demand response as defined in Article 27 of Regulation (EU) 2016/1388, shall provide the TSO and the DSO at the day-ahead and close to real-time and on behalf of all of its distribution-connected demand facilities, with the following data: structural minimum and maximum active power available for demand response and the maximum and minimum duration of any potential activation of demand response in a specific geographical area defined by the TSO and DSO; a forecast of unrestricted active power available for the demand response and any planned level of demand response in a specific geographical area defined by the TSO and DSO; real-time active and reactive power; and a confirmation that the estimations of the actual values of demand response are applied.
← art_51__para_3__text_1 · All articles · Article 52 →
Source: EUR-Lex (Cellar) · retrieved 2026-11-04 · Text as adopted (Official Journal); later amendments are not incorporated in this text.