8.
Member States may establish a simple-notification procedure for grid connections for repowering projects as referred to in Article 17(1). Where Member States do so, repowering shall be permitted following notification to the relevant authority where no significant negative environmental or social impact is expected. That authority shall decide within six months of receipt of a notification whether this is sufficient. Where the relevant authority decides that a notification is sufficient, it shall automatically grant the permit. Where that authority decides that the notification is not sufficient, it shall be necessary to apply for a new permit and the time-limits referred to in paragraph 6 shall apply.