art_16__para_8__text_1
Text with EEA relevance.
Member States may establish a simple-notification procedure for grid connections for repowering projects as referred to in Article 17(1). Where Member States do so, repowering shall be permitted following notification to the relevant authority where no significant negative environmental or social impact is expected. That authority shall decide within six months of receipt of a notification whether this is sufficient.
National law under this provision
1 national measure recorded under this provision, in 1 form — sign in to view the analysis.
← 8. · All articles · art_16__para_8__text_2 →