For the purpose of this paragraph, ‘start of works’ means either the start of construction works on the investment or the first firm commitment to order equipment or other commitment that makes the investment irreversible, whichever is the first in time. Buying of land and preparatory works such as obtaining permits and conducting preliminary feasibility studies are not considered as start of works. For take-overs, ‘start of works’ means the moment of acquiring the assets directly linked to the acquired establishment.