Regional coordination centres shall support transmission system operator in calculating the maximum entry capacity available for the participation of foreign capacity in capacity mechanisms taking into account the expected availability of interconnection and the likely concurrence of system stress between the system where the mechanism is applied and the system in which the foreign capacity is located.