(a)
Text with EEA relevance.
from 4 July 2019 at the latest, generation capacity that started commercial production on or after that date and that emits more than 550 g of CO_(2) of fossil fuel origin per kWh of electricity shall not be committed or to receive payments or commitments for future payments under a capacity mechanism;
← art_22__para_4__text_1 · All articles · art_22__para_4__point_a__text_1 →