art_22__para_4__point_a__text_1
Text with EEA relevance.
from 4 July 2019 at the latest, generation capacity that started commercial production on or after that date and that emits more than 550 g of CO_(2) of fossil fuel origin per kWh of electricity shall not be committed or to receive payments or commitments for future payments under a capacity mechanism;
← (a) · All articles · (b) →
Source: EUR-Lex (Cellar) · retrieved 2026-10-30 · Text as adopted (Official Journal); later amendments are not incorporated in this text.