art_3__para_2__para__2
In relation to installations carrying out activities referred to in Annex I which fall within the scope of the directive before 4 August 2024. Article 15(3) shall apply when the permit is updated within four years of publication of, or granted after, decisions on BAT conclusions that have been published after 1 July 2026 in accordance with Article 13(5) relating to the main activity of an installation, or when the permit is updated pursuant to Article 21(5), or by 1 September 2036, whichever is the earlier.
← art_3__para_2__para · All articles · art_3__para_2__para__3 →
Source: EUR-Lex (Cellar) · retrieved 2026-10-13 · Text as adopted (Official Journal); later amendments are not incorporated in this text.