7. No later than one month from the date of acknowledgement referred to in paragraph 6 of this Article, the single point of contact concerned shall draw up, in close cooperation with the project promoter and other competent authorities concerned, a detailed schedule for the permit-granting process. The schedule shall be published by the project promoter on the website referred to in Article 8(5). The single point of contact concerned shall update the schedule in the event that there are significant changes that potentially affect the timing of the comprehensive decision.