8. The single point of contact concerned shall notify the project promoter when the environmental impact assessment report referred in Article 5(1) of Directive 2011/92/EU is due, taking into account the organisation of the permit-granting process in the Member State concerned and the need to allow sufficient time to assess the report. The period between the deadline for the submission of the environmental impact assessment report and the actual submission of that report shall not be counted towards the duration of the permit-granting process referred to in paragraphs 1 and 2 of this Article.