9. Where the consultation pursuant to Article 1(2), point (g)(ii), of Directive 2011/92/EU results in the need to supplement the environmental impact assessment report with additional information, the single point of contact concerned may give the project promoter the opportunity to provide additional information. In such a case, that single point of contact shall notify the project promoter when the additional information is due, which shall be in no less than 30 days after the notification. The period between the deadline for providing the additional information and the submission of that information shall not be counted towards the duration of the permit-granting process referred to in paragraphs 1 and 2 of this Article.