Section 54(2)
Subject to paragraph (3), the planning permission to which the ROMP application relates shall not authorise any minerals development (unless the Secretary of State has made a screening direction to the effect that ROMP development is not EIA development) if the applicant or the appellant does not— write to the authority or Secretary of State within the 6 week or other period agreed pursuant to regulation 11(4), 13(6) or 14(7); submit an environmental statement and comply with regulation 20(6) within the period specified by the authority or the Secretary of State in accordance with paragraph (1) or within such extended period as is agreed in writing; provide additional information within the period specified by the authority, the Secretary of State or an inspector in accordance with paragraph (1) or within such extended period as is agreed in writing; or where a notification under regulation 6(5), 7(3), 15(3) or 16(3) has been received, provide the additional information requested within 3 weeks beginning with the date of the notification, or within such extended period as may be agreed in writing with the authority or Secretary of State, as the case may be.
← 1 · All articles · 3 →
Source: legislation.gov.uk · retrieved 2026-07-30